Start shutdown manpower planning months ahead: turn the work scope into a trade-by-trade histogram, plan two shifts, allow time for visas, gate passes and site inductions, include support roles such as fire watch and permit staff, and plan for summer heat-stress rules.

Start from the work scope, not the headcount
A shutdown manpower plan turns the approved work list into headcount by trade, day and shift, then accounts for mobilisation, permits and support roles. Start with shutdown and turnaround support and industrial manpower supply to match the scope. For outdoor summer work, check the applicable year's rules, including the official Saudi HRSD notice.
Build the headcount from dated work packages, not a single peak number detached from the schedule.
The trades a typical turnaround needs
- Mechanical: fitters, millwrights and mechanical maintenance technicians for exchangers, pumps and valves.
- Welding and fabrication: certified welders and pipe fitters for repairs and modifications.
- Lifting and access: riggers, signalmen and scaffolders, often Aramco-approved.
- Inspection and coating: NDT technicians, coating inspectors, blasters and painters.
- Safety and support: fire watch, hole watch, permit coordinators and HSE officers.
- Cleaning: industrial cleaning crews for vessels and tanks.
One shift vs two shifts for shutdown staffing
Shift coverage should follow the critical path, permit windows, site rules and the real productivity of each work package. A second shift extends the available work window; it does not automatically double output.
| Planning factor | Single shift | Two shifts |
|---|---|---|
| Coverage | Work proceeds during one planned daily window | Work can continue across a longer daily window where the site permits |
| Crew plan | One primary crew per trade, with relief and support as required | Separate crews or rotations plus supervisors and support for each shift |
| Coordination | One daily plan and fewer shift handovers | Structured handover, permit continuity and clear responsibility between shifts |
| Best fit | Work scopes that fit the available window and site access | Critical-path work where an extended window is approved and safely supported |
| Checks | Heat, access, permits, equipment and crew fatigue | The same checks, plus night supervision, lighting, transport and fatigue controls |
Leave time for mobilisation and compliance
In Saudi Arabia, people cannot simply arrive and start work. Allow time for:
- Visas, Iqama status and GOSI registration for every worker.
- Gate passes and site access approvals from the plant owner.
- Site safety inductions, medical checks and fit tests for respirators.
- Verification of certificates for welders, riggers, scaffolders and inspectors.
- Accommodation, meals and transport between camp and site.
These steps often take longer than recruitment itself, so start them weeks before the shutdown window.
Plan for the heat
For 2026, HRSD announced a midday outdoor work ban from 12:00 to 3:00 p.m. between 15 June and 15 September, along with preventive heat-stress measures. These dates are year-specific: check the official HRSD notice for the relevant year before scheduling work. Include shade, water, rest and site-specific heat-stress controls in the plan.
Demobilise as fast as you mobilised
Once the plant restarts, every extra day of manpower is cost. Plan demobilisation by trade: scaffolders and cleaners stay longest, specialist crews leave first. Close out permits, return gate passes and collect timesheets while people are still on site.
How Al Aitimad supports shutdowns
Our shutdown and turnaround service can cover mechanical, welding, coating, rigging, scaffolding, cleaning, fire watch and permit support, subject to scope and availability. We coordinate mobilisation and compliance, and can arrange cranes through equipment rental where the project requires them.
Conclusion
What to take away
Build the crew plan from the work list and daily schedule, then add time for mobilisation, site approvals, support roles and both shifts. Recheck the headcount against the live work plan as the shutdown approaches.